Lesson Learned





By: Richard Mollison

Report No.

4765

Discipline/Origin

Drilling
Own Experience

Well

CopernicusNo well selected

Date created

2022/08/23
1201 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Equipment
N/A

Deepsea Yantai


What happened in Surface section:
The use of normal HWDP Requires double handling from fingerboard to well center when running and pulling.

What Was Planned

Contracted rig HWDP results in additional handling time to make up due to middle joint upset, conflict with hydraracker.

What Was Learned

Time/ cost saving potential if double handling requirement removed

What Actions Are Required

Have thick wall drill pipe available included in the rig contract, this removes the need for double handling and time spent on critical path

Alternative approach, remove the middle joint upset on the top single of the stand of HWDP, this can be done in the metal workshop prior to ops. Additional cost associated vs rental cost of TWDP.

What Was Done

For Copernicus, double handling of the HWDP from the fingerboard to well center will be utilized